Australia Free Web Directory

Crudine Ridge Wind Farm in Mudgee, New South Wales | Energy company



Click/Tap
to load big map

Crudine Ridge Wind Farm

Locality: Mudgee, New South Wales

Phone: +61 1300 524 463



Address: aarons pass road Mudgee, NSW, Australia

Website: https://www.crudineridgewindfarm.com.au

Likes: 186

Reviews

Add review



Tags

Click/Tap
to load big map

25.01.2022 Are you a landholder interested in on farm renewables? Then this webinar may be just the ticket: https://www.farmrenewables.com.au/conference



25.01.2022 CWP Renewables are pleased to announce the Crudine Ridge Wind Farm has achieved a major milestone by securing registration on the 24th November 2020. Located 45km South of Mudgee, the 135MW Wind Farm will generate power for around 55,000 homes once operational and has created over 240 jobs during its construction. The CWP Renewables Team would like to thank AEMO, TransGrid and General Electric/Zenviron, along with all the Sub-contractors, many of whom were from the local area, for their efforts in getting the project to this stage.

24.01.2022 Blade Delivery Schedule for this week.

20.01.2022 Mental Health Monday rolled out at Crudine Ridge with all the shirts supplied to those who ordered them. Thank you to all involved and all the orders & donations received. Look out for your mates. #wts #windturbineservices #blackdoginstitute



15.01.2022 A Total Fire Ban has been declared for Tuesday 1st of December. Stay safe out there.

15.01.2022 Crudine Ridge Wind Farm 37 Pre Installations at a rate of 2.46 per week (including delays) above the 2.4 target. Regularly achieving 3 and 4 per week. The tea...m also installed blades on 4 turbines before completing the south section. Great effort by all involved. #windturbineservices #mammoet #zenviron #teamwork #safetyfirst See more

14.01.2022 Next weeks Blade Delivery Schedule



13.01.2022 Stay safe out there as more storms are predicted

13.01.2022 Next week will be the final Tower delivery to Crudine Ridge Wind Farm. See attached delivery schedule.

09.01.2022 Here's how a blade is lifted into place. If you look closely at the hub you'll see the "Blade Catchers" ready to guide the bale into its final resting place.

09.01.2022 Final Clearing Reports for Aarons Pass Road Upgrade available here: https://www.crudineridgewindfarm.com.au/aaronspassroad/

06.01.2022 This weeks Blade Delivery Schedule.



01.01.2022 If you’ve got what it takes to build a wind farm, then Wind Turbine Services has a job for you.