25.01.2022 Onsite works at 7 Toward Street Murrumbeena have continued to progress well in January, with ground floor brickwork and render panels almost complete in preparation for erection of perimeter scaffold. Internal plumbing rough in works have also commenced while install Roof sheets is expected to be completed in February.
22.01.2022 An inspirational design with a commitment to contemporary luxury makes this remarkable family home an exceptional find. Included in the sleek interiors are expansive open-plan living/dining, sitting room, hostess kitchen, outdoor entertaining alfresco area with a beautiful heated pool & streamlined windows letting inside & out merge seamlessly together. The elegant culinary kitchen is appointed with stone bench-tops, butlers’ pantry, excellent storage & high-end Miele applian...ces, including a double oven & built in coffee machine. Upstairs there are four bedrooms, three bathrooms & a retreat area. The master bedroom enjoys access to a rear terrace & luxurious light filled ensuite, while the second bedroom also includes an additional balcony at the front. The impressively modern home also features Grey Ironbark floors, gas fireplace, double garage with overhead storage, powder room, ducted heating & air conditioning through linear slots, central vacuum, laundry equipped with drying cupboard, pull-out ironing board & laundry chute. The decked alfresco area includes built in speakers, heater & fan creating an expansive outdoor area which can be used all year round. The resort style pool area is complimented by an impressive water feature & elegantly sculptured landscape design. Other amenities include video monitored entry, alarm system, double height void above the entry & 3m ceilings throughout all formal areas. Close to buses, trams, excellent schools, shops, cafe’s & Caulfield Park, Plaza, Racecourse & Station.
21.01.2022 A flurry of activity onsite in December with both first floor slab and lift shaft completed ahead of schedule. A fair bit of preparation was also done towards the end of the year so to hit the ground running in the New Year. Wishing everyone a happy and healthy new year. Looking foreword for another exciting and busy 2018.
19.01.2022 The latest collaboration between acclaimed Perkins Architects and Keystone BMV Group, Ripponlea On The Park represents the benchmark in luxury inner city living. A boutique development of ten luxury residences articulates both cutting edge architecture and an environmentally sustainable design. Overlooking the stunning Ripponlea Gardens these executive homes are within minutes of public transport and short Train or Tram ride away from the CBD. Perfectly located between the upmarket Elwood & St Kilda hubs and within walking distance of the Glenhuntly road & Carlisle street precincts, Ripponlea on the Park offers a vast selection of restaurants, cafes and shops. Sophisticated finishes blended seamlessly with state of the art appliances deliver a relaxed living environment, while providing the convenience of a modern lifestyle.
19.01.2022 For latest updates visit www.instagram.com/kbmv_developments
19.01.2022 Great progress, finish line in sight..
17.01.2022 Nearing completion.
16.01.2022 Skilfully designed by Ian Perkins Architects is this sensational block of townhouses, comprising of both downstairs and upstairs living areas. Kitchen with Emporite cupboards with stone bench tops, glass splashbacks & stainless steel appliances. Laundry, powder room, upstairs features main bedroom with ensuite bathroom, BIR’s and outdoor balcony. Features also include reverse cycle heating/ cooling, undercover parking and polished timber floors. Perfectly positioned in vibrant Elsternwick; close to shops, cafes and transport.
15.01.2022 Work at Beaux progressing well despite the wet weather with Piling works completed and commencement of capping beam reinforcement works today.
15.01.2022 Comprising 12 boutique town houses with cutting-edge internal and external design features, revel in the distinguished metropolitan life-style you deserve. Classy, clean and contemporary features define the ground floor, comprising luxuriously light-filled and spacious open-plan kitchen, living, dining and private balcony. The elegant timber floor is tastefully complemented by a white island kitchen bench. Functionality and glamour meet in the kitchen, equipped with ultramode...rn, premium appliances including mirror finish to the splash-back to create the ultimate culinary experience. With two bedrooms (both with BIR’s), sparkling central bathroom with euro laundry, plus a downstairs powder room and single car space, this property will not disappoint. Murrumbeena is located 13 km south-east of the CBD. Bounded by Princes Hwy in the north and North Rd in the south, Murrumbeena is a predominantly residential suburb in Melbourne’s south-east. The suburb is split by the Dandenong Railway Line, with the area surrounding the Murrumbeena Station providing a small retail and commercial focus. The suburb also features a number of parks such as the Murrumbeena Park and the Duncan MacKinnon Reserve.
14.01.2022 With brickwork completed last week & plastering works now well underway, the building at 7 Toward Street, Murrumbeena is really taking shape both inside & out. Progress on site still going well, so expecting even bigger month in April following the Easter long weekend.
09.01.2022 New level of sophistication and attention to detail heralds a new standard in apartment living. La Riviere is a boutique development of only 12 apartments created to be the best and brightest in a brilliant location close to trams and Elsternwick’s vibrant hustle and bustle. Luxury appointments include polished timber floors, Emporite kitchen incorporating Miele stainless steel appliances, inviting courtyard, zoned heating/airconditioning and video security. Lift access to basement garaging adds convenience to impressive contemporary comfort.
08.01.2022 Beaux - 7 Toward Street, Murrumbeena. Good progress in April again, with much of the cladding works completed, lift installed and scaffolding removed last week. Focus on site in May will be on internal works with joinery, tiling as well car stacker installation commencing this week
08.01.2022 Demolition Completed and Builder Appointed with construction due to commence August 2017.
05.01.2022 Making great progress at 7 Toward St, Murrumbeena. Basement walls and slab were completed in the past week. Ground floor suspended slab targeted for completion end of October.
04.01.2022 Toward Street works continue to progress at record speed with Level 1 block walls and steel completed at the end of November. We expect to have the top floor slab poured before the Christmas break. Very pleased with progress on site