Australia Free Web Directory

Kings Surf Apartments in Caloundra, Queensland | Beach resort



Click/Tap
to load big map

Kings Surf Apartments

Locality: Caloundra, Queensland

Phone: +61 408 758 508



Address: 5 Ormonde Terrace 4511 Caloundra, QLD, Australia

Website:

Likes: 45

Reviews

Add review



Tags

Click/Tap
to load big map

24.01.2022 Back half of basement slab being poured.



23.01.2022 Half basement slab poured. Other half next week. Please hold off the rain!

23.01.2022 Lift and drainage pits and footings for main support structure. Next major milestone is basement slab

22.01.2022 Basement excavation half way



22.01.2022 Old Crystal Waters block of 6 flats demolished today.

22.01.2022 Tenants moved out yesterday. Trees cut down last week. Construction Fencing erected this morning. Electricity gets cut off next. Then demolition starts.

20.01.2022 Choosing external building colours for final Building Approval from Council. Colourbond colours surf mist and monument chosen.



19.01.2022 Basement excavated half way down while anchors are drilled into the sheet piling to secure them. Once anchors installed, basement will be excavated fully.

18.01.2022 Builders are drilling about 200 holes 600mm wide around the basement perimeter in preparation for sheet piling then excavation of basement.

18.01.2022 Photos taken yesterday. The first batch of concrete has been poured. The largest pit is the bottom of elevator shaft. The other two smaller pits, which will be under floor of basement, are used for basement drainage and will host a sump pump.

18.01.2022 Construction officially commenced 21 Jan 2021.

16.01.2022 Scaffolding erected yesterday. Demolition starts Monday.



16.01.2022 Installing sheet piling across the back of the basement location in preparation for excavating.

12.01.2022 Ready for demolition. Scaffolding across front and side.

09.01.2022 Favourite work site for construction crew. This site is attracting a lot of interest.

09.01.2022 View from the first floor (unit 3 & 4) and the second floor (unit 5 & 6).

07.01.2022 Basement work showing install of anchors and excavation. Basement will be ready for pouring concrete by end of next week. Currently 1.5 weeks behind schedule.

05.01.2022 Basement excavation started this morning.

05.01.2022 Basement being excavated to full depth now. Excavation going smoothly. No unexpected rock.

04.01.2022 Sheet piling around basement wall expected to finish next week with basement excavation starting 22nd Feb

Related searches