Perth Earth | Demolition & excavation company
Perth Earth
Phone: +61 410 171 935
Reviews
to load big map
24.01.2022 Putting new fleet excavator to the test today.
21.01.2022 Just carting a bit of sand today. ........ In 42 degrees. Beaut day.
20.01.2022 Sorrento Siteworks! 300m3 limestone ripped and removed offsite. 600mm split level sand pad trimmed/compacted with compaction certificate supplied, ready for Granos..
18.01.2022 Love early morning starts. The lads into it early onsite this morning...
18.01.2022 Lake Karrinyup Country Club.... Tee construction, turf removal etc. No good hitting the balls so endeavour to dig the track up instead!!
18.01.2022 Site cleared, raked clean,soakwells installed,sand carted in/compacted ready to build!
18.01.2022 Tight access laneway housepad. Site stripped/cleared, sand carted into site, compacted with compaction certificate. Ready to start building!
17.01.2022 Hope everyone is having a safe holiday & we wish everyone a happy new year for 2018. We will be back on deck 8/1/18 for all your earthmoving & cartage needs so give us a call.
17.01.2022 Site works Burns beach.. Site stripped/cleared, raked, stormwater and rainwater tanks installed, pool excavated, shoring installed, backfilled, pad levels raised/compacted, compaction certificate supplied, ready for granos to commence...
17.01.2022 Another remedial earthworks project complete. Give us a call for a quote or advise on your next subdivision/ WAPC approval earthworks requirements.
16.01.2022 South guildford remedial earthworks...
15.01.2022 Could be worse views to start the week...
15.01.2022 Another demolition /site works project started.
15.01.2022 New 15th pro tee built this week at Lake Karrinyup Golf Club. Good job done by Muzza - 35 loads of sand and not stuck once. Ready for retic & turf.
14.01.2022 Our team at the end of this week were engaged to supply and stockpile 1400 tonne of Carramar plasterers sand to Lake Karrinyup golf Course for there up and coming 9 hole greens renovation/construction project.. Contact us for a quote on your next material supply/disposal requirements!!
14.01.2022 Couple of pics from our contract works on Great North Connect. Perth Earth always willing to come up with solutions to tackle any jobs.
14.01.2022 End of week power raking, turf prep...
14.01.2022 Muchea pond relining works...
12.01.2022 Top morning for it, on the waterfront this morning!!
12.01.2022 Introducing our newest Perth Earth member Stace Keen! Stace has more than 20 years experience in the construction industry and has worked on major projects such as Jimblebar BHP water supply mains, Gateway infrastructure upgrades and other high profile large scale projects in a recognised senior role. Stace will be taking on the role of Services and Civil Manager.... Welcome Stace!
11.01.2022 Finally the sun is shining.....
10.01.2022 X4 unit development, Morley.. Site cleared, stripped, compacted...x 4 sandpads with compaction certificates at completion ready for building to commence..
10.01.2022 Basement excavation - Salter Point 150m3 Topsoil/grass stripped 600m3 sand excavated/removed 100m3 stockpiled for backfill Compacted ready for retaining walls.
10.01.2022 Bit of work we are currently doing around Northbridge tunnel
09.01.2022 Siteworks Cannington.. *Cleared site of vegetation *Excavated/Compacted bases for engineers sign off *Imported cleanfill/compacted with compaction certificates *X4 sand pads ready to build
06.01.2022 Perth Earth recently undertook construction of a perched water table green, on the newly designed 1st hole at Collier Park golf course. Full credit to Gun operator Kevin Busch (Bushy) for the full completion of this project start to finish, alongside course architect Terry Gale and course superintendent Peter Beach.
06.01.2022 Check out our new Projects page to see some of Perth Earths latest work. http://www.perthearth.com.au/projects/
04.01.2022 Mt Helena site works.. Site stripped and base excavated with rockbreaker.. retaining wall built, backfilled, 600mm sand pad constructed ready for building..
03.01.2022 Perth Earth at Lake Karrinyup Country Club helping out with our talented & experienced operators along with some of our fleet of machinery on the back nine green & bunker refurbishment project.
03.01.2022 This weeks project! Scarborough basement excavation..
02.01.2022 Demolition Job Balga! Full house demo/ site cleared and raked to 800mm
01.01.2022 Site clearing thornlie... Site cleared, raked and levelled. Ready for clients to subdivide and sell rear block...
Related searches
- Wired Store
Electrician Businesses Local service Home improvement Home security company Automation service
+61 1300 782 125
35 likes
- Unique 2nd Space
Businesses Local service Home improvement Construction company Contractor Disability service
+61 460 966 604
29 likes