22.01.2022 3. Formwork for the slab and plumbing roughed in



21.01.2022 5. The frames for the ground floor started to go up.

17.01.2022 4. David and I set out the waffle pods and put in the steel then the slab was poured

09.01.2022 2. After demo. The old laundry and deck off the back door are gone. Excavation creates a flat area for the slab. All measurements crucial to make sure the upper floors align.



04.01.2022 6. We manhandled the header beams for the sliding doors into place