Australia Free Web Directory

Range Steel Fabrications in Toowoomba City | Industrial company



Click/Tap
to load big map

Range Steel Fabrications

Locality: Toowoomba City



Address: 3 Stark Court Harristown 4350 Toowoomba City, QLD, Australia

Website: www.linkedin.com/company/range-steel-fabrications

Likes: 210

Reviews

Add review



Tags

Click/Tap
to load big map

25.01.2022 St Ritas College completed. High spec finish down to custom carpet made and imported from Denmark.



25.01.2022 Toowoomba State High School Link Bridge install completes this project, Linking Old with new

25.01.2022 Plant Deck Trusses complete for Buderim Coles.Ready for Galvanising

23.01.2022 1st Truss Spliced and Complete



23.01.2022 Meadowbrook Project Underway 2 Crane Crew putting this one up double time

20.01.2022 Heritage Seeds Warehouse close to completion on Vision Street

20.01.2022 1st load of Buderim Coles on its way for Top Coating



20.01.2022 3rd Truss installed and Bondeck has been laid ready for concrete pour

19.01.2022 Bondeck Slab complete

19.01.2022 St Marys Toowoomba Fabrication has commenced. Auditorium steel portion - Main Trusses

19.01.2022 Meadowbrook project is ticking away

19.01.2022 Good Headway being made at Meadowbrook



18.01.2022 Darra Service Centre Is progressing well. Truck Canopy , Car canopy and Retail close to completion

17.01.2022 This is the 1st peice of steel to take on our new barcoding system. Has been quite a long process to get to this point. Our goal is to limit the data entry and mistakes concerning our load inventories. Limiting the labour time to generate accurate loadsheets has also been a driving element behind this new process.

16.01.2022 Mort Street Project close to completion. Site welding to close out

15.01.2022 Meadowbrook 5th load of steel delivered. Approx 93.5 Tonne delivered with the balance of 26 Tonne to come

15.01.2022 All the Assets are active this morning!

15.01.2022 St Marys Toowoomba Project is nearly complete. Pretty tough detailing and fabrication on this one due to complex roof lines.

15.01.2022 Auscoil Project Complete

13.01.2022 Auscoil Steel erection underway

12.01.2022 Current progress from site this week. Plenty of steel deliveries to keep up with construction to get to this point

11.01.2022 Spidercrane lifted up onto Level 4 to lift in the Plant Decks and Main Roof Steel at St Ritas College

11.01.2022 Hold Down Bolt templates cut on our plasma with ID numbers and centre points. All that is required now is for them to be installed accurately onsite........

10.01.2022 St Ritas College is just about complete with final finishes left. This project presented us with many challenges and obstacles which we overcame. Good to see it near completion.

10.01.2022 Cairns Homeconsortium Progress This is our 6th Homeco Project

10.01.2022 Oakey Beef Coldroom is up and small portions of steel left to install Total Project weight approx 230T

09.01.2022 Loads 4 and 5 ready for Despatch to Kingsbury Warehouse

09.01.2022 Rode Road Project completed. The Curvy facade's went up extremely well.

09.01.2022 Northlakes Storage facility is underway with 2 phases of steel left to deliver and erect

08.01.2022 Oakey Beef project is well underway. Approx 230T Dual cranes are working in unicen to make the erection timeframe. Site crew is working really well.

08.01.2022 Heritage Seeds Complete

08.01.2022 New signage has finally gone up

07.01.2022 St Ritas is coming to a close. The project has gone extremely well based on the complexity of the Project.Thanks needs to go to the Steel detailer as this is a critical component on a build of this nature. Curved Bridges complete with Cafco items left to install.

06.01.2022 Steel going up for the new Mazda service centre at Springwood

05.01.2022 Ist Load of Auscoil steel ready for Delivery to site

05.01.2022 1st 20T of steel going to be galvanised for the Wandoan Battery Facillity

04.01.2022 Karcher is opening thier own Carwash on Beaudesert Rd @ Acacia Ridge Range Steel Fabrications is nearly complete on this one.

04.01.2022 Bylaser supplies RSF with Laser cut processed plates.Thier customer service is second to none. Brad from Bylaser cooked up breakfast for our staff with their new BBQ Trailer. Thanks for the bacon & Egg rolls and the service over 2020.

04.01.2022 Longest Member we have carried to date 26.1M Coles Buderim L2

04.01.2022 Highlands Church Steel has finally commenced erection

03.01.2022 Burpengary Station Village has finally kicked off after a long delay due to Covid 19 Approx 120T of Structural Steel. Phases 1 and 2 Steel portions erected

03.01.2022 Rode Road Project completed. The Curvy facades went up extremely well.

02.01.2022 The CNC Plasma hard at it cutting the HD Bolt templates for the next project in Bundaberg.

02.01.2022 Both Centre Trusses installed with Infill steel to complete

02.01.2022 Cleaned up ready for next weeks movements

01.01.2022 Main Roof and Level 5 Western plant deck close to completion. Level 5 Eastern Plant deck and Main roof to finish. Final Phase is the Lower Eastern Roof and Twisted Wall + Curved Bridges which will close out this project.

01.01.2022 Auditorium Seating Steel Installed at St Ritas Level 2

Related searches