Range Steel Fabrications in Toowoomba City | Industrial company
Range Steel Fabrications
Locality: Toowoomba City
Address: 3 Stark Court Harristown 4350 Toowoomba City, QLD, Australia
Website: www.linkedin.com/company/range-steel-fabrications
Likes: 210
Reviews
to load big map
25.01.2022 St Ritas College completed. High spec finish down to custom carpet made and imported from Denmark.
25.01.2022 Toowoomba State High School Link Bridge install completes this project, Linking Old with new
25.01.2022 Plant Deck Trusses complete for Buderim Coles.Ready for Galvanising
23.01.2022 1st Truss Spliced and Complete
23.01.2022 Meadowbrook Project Underway 2 Crane Crew putting this one up double time
20.01.2022 Heritage Seeds Warehouse close to completion on Vision Street
20.01.2022 1st load of Buderim Coles on its way for Top Coating
20.01.2022 3rd Truss installed and Bondeck has been laid ready for concrete pour
19.01.2022 Bondeck Slab complete
19.01.2022 St Marys Toowoomba Fabrication has commenced. Auditorium steel portion - Main Trusses
19.01.2022 Meadowbrook project is ticking away
19.01.2022 Good Headway being made at Meadowbrook
18.01.2022 Darra Service Centre Is progressing well. Truck Canopy , Car canopy and Retail close to completion
17.01.2022 This is the 1st peice of steel to take on our new barcoding system. Has been quite a long process to get to this point. Our goal is to limit the data entry and mistakes concerning our load inventories. Limiting the labour time to generate accurate loadsheets has also been a driving element behind this new process.
16.01.2022 Mort Street Project close to completion. Site welding to close out
15.01.2022 Meadowbrook 5th load of steel delivered. Approx 93.5 Tonne delivered with the balance of 26 Tonne to come
15.01.2022 All the Assets are active this morning!
15.01.2022 St Marys Toowoomba Project is nearly complete. Pretty tough detailing and fabrication on this one due to complex roof lines.
15.01.2022 Auscoil Project Complete
13.01.2022 Auscoil Steel erection underway
12.01.2022 Current progress from site this week. Plenty of steel deliveries to keep up with construction to get to this point
11.01.2022 Spidercrane lifted up onto Level 4 to lift in the Plant Decks and Main Roof Steel at St Ritas College
11.01.2022 Hold Down Bolt templates cut on our plasma with ID numbers and centre points. All that is required now is for them to be installed accurately onsite........
10.01.2022 St Ritas College is just about complete with final finishes left. This project presented us with many challenges and obstacles which we overcame. Good to see it near completion.
10.01.2022 Cairns Homeconsortium Progress This is our 6th Homeco Project
10.01.2022 Oakey Beef Coldroom is up and small portions of steel left to install Total Project weight approx 230T
09.01.2022 Loads 4 and 5 ready for Despatch to Kingsbury Warehouse
09.01.2022 Rode Road Project completed. The Curvy facade's went up extremely well.
09.01.2022 Northlakes Storage facility is underway with 2 phases of steel left to deliver and erect
08.01.2022 Oakey Beef project is well underway. Approx 230T Dual cranes are working in unicen to make the erection timeframe. Site crew is working really well.
08.01.2022 Heritage Seeds Complete
08.01.2022 New signage has finally gone up
07.01.2022 St Ritas is coming to a close. The project has gone extremely well based on the complexity of the Project.Thanks needs to go to the Steel detailer as this is a critical component on a build of this nature. Curved Bridges complete with Cafco items left to install.
06.01.2022 Steel going up for the new Mazda service centre at Springwood
05.01.2022 Ist Load of Auscoil steel ready for Delivery to site
05.01.2022 1st 20T of steel going to be galvanised for the Wandoan Battery Facillity
04.01.2022 Karcher is opening thier own Carwash on Beaudesert Rd @ Acacia Ridge Range Steel Fabrications is nearly complete on this one.
04.01.2022 Bylaser supplies RSF with Laser cut processed plates.Thier customer service is second to none. Brad from Bylaser cooked up breakfast for our staff with their new BBQ Trailer. Thanks for the bacon & Egg rolls and the service over 2020.
04.01.2022 Longest Member we have carried to date 26.1M Coles Buderim L2
04.01.2022 Highlands Church Steel has finally commenced erection
03.01.2022 Burpengary Station Village has finally kicked off after a long delay due to Covid 19 Approx 120T of Structural Steel. Phases 1 and 2 Steel portions erected
03.01.2022 Rode Road Project completed. The Curvy facades went up extremely well.
02.01.2022 The CNC Plasma hard at it cutting the HD Bolt templates for the next project in Bundaberg.
02.01.2022 Both Centre Trusses installed with Infill steel to complete
02.01.2022 Cleaned up ready for next weeks movements
01.01.2022 Main Roof and Level 5 Western plant deck close to completion. Level 5 Eastern Plant deck and Main roof to finish. Final Phase is the Lower Eastern Roof and Twisted Wall + Curved Bridges which will close out this project.
01.01.2022 Auditorium Seating Steel Installed at St Ritas Level 2
Related searches
- Irribiz Greenworks Mt Evelyn
Home improvement Industrial company Agricultural service Water treatment service
+61 3 9037 7499
Unit 3/5 Clancys Road, Mt Evelyn 3796 Melbourne, VIC, Australia
98 likes
-
- Industrial Equipment Maintenance
Businesses Industrial company Commercial and industrial
+61 412 204 770
25 likes
- ISG Electrical
Electrician Industrial company Commercial and industrial Metal fabricator
+61 2 4982 2244
5 Sky Clos 2316 Taylors Beach, NSW, Australia
54 likes