Signature Property Group | Company
Signature Property Group
Reviews
to load big map
25.01.2022 Things are moving along faster and faster as we speed toward the completion of 202 Northcott Drive, Adamstown Heights. Milestone tasks achieved last week: * Unit 1, 2 & 3 Ground floor roofing completed.... * Units 1, 2 & 3 Insulation installed. * Unit 4 & 5 Timber flooring installed. * Units 4 & 5 Stone benchtops installed. Milestone tasks achieved this week: * Unit 1, 2 & 3 Scaffolding to be removed. * Unit 1, 2 & 3 Ground floor eaves. * Unit 1, 2 & 3 Internal linings to commence. * Unit 4 & 5 Splashbacks to be installed. * Unit 4 & 4 Ground floor mould out. * External Works Driveway/retaining walls to be trimmed and levelled where required.
23.01.2022 We are getting closer and closer to the finish line and WOW these homes are just stunning: Please see below the progress of site works. Milestone tasks achieved this week:... Unit 1, 2 & 3 Internal final paint first floor complete. Units 1, 2 & 3 Carpet commenced. Units 1, 2 & 3 Shower screens and mirrors installed. External Works Stormwater connection to detention tank. External Works Detention tank waterproofed. External Works Detention tank sand filter installed. External Works Detention tank backfilled. External Works Detention tank lid formed and reo installed. External Works Entry pavers installed to Units 1 & 5. Milestone tasks to be achieved next week: Units 1, 2 & 3 Carpet to be completed. Units 1, 2 & 3 Final paint to ground floor to be completed. Units 1, 2 & 3 Final clean External Works Flyscreens to be delivered. External Works Boundary wall final panels to be installed. External Works Render to front retaining walls. External Works Timber screens to be installed. External Works Letterbox footing and blockwork to be installed. External Works Landscaping to be completed. External Works Driveway works to be completed.
20.01.2022 Timeless, Refined & Meticulously Crafted - Welcome to CORA For more information please contact Kapalua Advisory To learn more search WHITEBRIDGE on Realestate dot com.... Looking forward to sharing the CORA journey with you. Only TWO out of four F O R S A L E!!!
19.01.2022 Progress... All windows and doors in by end of week, brick work complete and ready to render with any luck by weeks end also. Things are running smooth!
17.01.2022 We are getting closer and closer to the finish line and WOW these homes are just stunning: Please see below the progress of site works. Milestone tasks achieved this week:... Unit 1, 2 & 3 Internal final paint first floor complete. Units 1, 2 & 3 Carpet commenced. Units 1, 2 & 3 Shower screens and mirrors installed. External Works Stormwater connection to detention tank. External Works Detention tank waterproofed. External Works Detention tank sand filter installed. External Works Detention tank backfilled. External Works Detention tank lid formed and reo installed. External Works Entry pavers installed to Units 1 & 5. Milestone tasks to be achieved next week: Units 1, 2 & 3 Carpet to be completed. Units 1, 2 & 3 Final paint to ground floor to be completed. Units 1, 2 & 3 Final clean External Works Flyscreens to be delivered. External Works Boundary wall final panels to be installed. External Works Render to front retaining walls. External Works Timber screens to be installed. External Works Letterbox footing and blockwork to be installed. External Works Landscaping to be completed. External Works Driveway works to be completed.
17.01.2022 Another great week onsite with a lot achieved. Still ahead of schedule and things running smooth. Milestone tasks achieved this week: Unit 1, 2 & 3 Complete fascia gutter to unit 1. Unit 1, 2 & 3 Roof sheeting completed... Units 1, 2 & 3 Arial’s installed to roof. Unit 4 & 5 Garage doors installed. Units 4 & 5 - Internal mold to the first floor completed. Unit 4 & 5 First 2 coats of paint completed (Final coat at the end of the project). Milestone tasks achieved next week: Unit 1, 2 & 3 Commence external cladding. Unit 4 & 5 Remove scaffolding. Unit 4 & 5 Tiling to bathrooms and laundries to commence. Units 4 & 5 Rendering to commence.
17.01.2022 Milestone tasks achieved last week: Unit 1, 2 & 3 First-floor mould out works continued. Unit 1, 2 & 3 Electrical fit off. Unit 1, 2 & 3 Plumbing fit off. Unit 1, 2 & 3 Unit 3 pergola installed.... Unit 1, 2 & 3 External ground floor painting commenced. Units 4 & 5 Pergolas installed. External Works Reinforcement to external stairs installed. External Works Water tank slabs poured. External Works Water tanks delivered. Unit 4 and 5 connected. External works Soil delivered and spread to Units 1, 2 and back yards. See more
16.01.2022 This weeks action on site at 202 Northcott Drive, Adamstown Heights. * Unit 1, 2 & 3 First floor painting completed. * Units 1, 2 & 3 First floor downpipes installed. * Unit 1, 2 & 3 First floor scaffolding removed. Ground floor scaffolding adjusted for roofing.... * Unit 4 & 5 Electrical fit off to walls. * Units 4 & 5 Mechanical fit off. * Unit 4 & 5 Laundry joinery installed. See more
12.01.2022 Hampton Residences is now completed and OC has been issued. Well done to our team and thank you for all your effort on this project. Looking forward to the launch of our new project CORA!... Coming soon......
05.01.2022 We have started the week with some great milestones reached. The roof for townhouse 4 and 5 installed tomorrow and brickwork for these two now complete ready for cladding to commence and all acoustic walls installed. Windows and doors to all dwellings installed and brickwork to townhouse 1, 2 and 3 to continue. Lots happening onsite and we love sharing the progress with you all. *Update on sales: Only 1 left at the time of writing this post
05.01.2022 Milestone tasks achieved last week: Unit 1, 2 & 3 First-floor mould out works continued. Unit 1, 2 & 3 Electrical fit off. Unit 1, 2 & 3 Plumbing fit off. Unit 1, 2 & 3 Unit 3 pergola installed.... Unit 1, 2 & 3 External ground floor painting commenced. Units 4 & 5 Pergolas installed. External Works Reinforcement to external stairs installed. External Works Water tank slabs poured. External Works Water tanks delivered. Unit 4 and 5 connected. External works Soil delivered and spread to Units 1, 2 and back yards. See more
03.01.2022 Thanks to everyone for the massive effort this week. A lot of big changes on site and everything is looking great! Goals achieved this week: Unit 1, 2 & 3 External cladding and eaves commenced. Unit 1, 2 & 3 Electrical rough in completed.... Unit 1, 2 & 3 First floor render completed. Unit 4 & 5 Scaffolding removed. Units 4 & 5 Rendering commenced. Unit 4 & 5 Floor tiles complete ready for wall tiling/grout. See more
03.01.2022 We have been working hard to get unit 4 completed and ready for open homes while still pushing forward with the quality build of units 1,2,3 and 5. Milestone tasks achieved last week: Unit 1, 2 & 3 Floor tiles completed. Unit 1, 2 & 3 First floor mould out commenced.... Unit 1, 2 & 3 Entry doors painted. External Works Concrete Hob to Unit 4 installed. External Works Landscaping to Unit 4 installed. External Works Driveway grade/levelling. Home four completely styled and cleaned. Open homes held 10:30am & 2pm Saturday 6th April, contracts in play Professional photography of unit 4 ready for rebrand online Milestone tasks to be achieved this week: Units 1, 2 & 3 First floor mould out to be completed. Units 1, 2 & 3 Joinery to commence. Units 4 & 5 Commence pergolas. External Works Driveway grade/levelling ready for concreters. External Works Waterproofing/backfilling to RW1.
01.01.2022 The week that was: Unit 4 & 5 Roofing complete. Unit 4 & 5 Eave Sheets complete. Unit 4 & 5 Commence external cladding. Unit 1, 2 & 3 Ground floor trusses complete.
01.01.2022 Another amazing week on site at Hampton Residences. Unit 1, 2 & 3 Fascia and gutter completed (units 2 & 3). Unit 1, 2 & 3 Scaffolding to Unit 1. Unit 1, 2 & 3 Acoustic ply completed (units 2 & 3).... Units 1, 2 & 3 Plumbing rough in completed. Unit 4 & 5 internal lining works completed. Unit 4 & 5 Internal staircases/handrails completed. Unit 4 & 5 - Waterproofing to wet areas. Unit 4 & 5 internal mould out to first floor commenced. Ausgrid Isolation and tiger tail works to mains completed. See more