20.01.2022 Stoney Creek Bridge Update - The approach road is almost complete and traffic is now on the new Stoney Creek bridge. The bridge has no guardrail yet, so drivers are asked to slow down and proceed with caution.
20.01.2022 High river flows put Little River Bridge to the test. https://au.prime7.yahoo.com//downpour-a-chance-to-test-fl/
16.01.2022 Little River Bridge Update. A $450,000 project to repair the Little River Bridge is almost complete. The bridge is on track to open to the public early next week.
07.01.2022 The start of the East - West Gilmore Bridge construction. The bridge planks have arrived and the 200T crane placed them into position today. In total there are 12 planks with each plank weighing 19.3T and 15 metres in length! These photos were taken this morning (nice backdrop on a sunny day) with 3 planks still to be positioned. Yet another step closer to finalising our Flood Recovery Program.... Remaining work include construction of bridge approaches, stream diversion (so stream is realigned to be under the mid bridge span), and embankment protection works. Completion is expected to be towards the end of May and the bridge will be reopened to traffic.
03.01.2022 Goobarragandra Road Update. The Goobarragandra Road was all but washed away in the flood of 2012, but is now better than ever.