Bns Builders | Company
Bns Builders
Phone: 0407805029
Reviews
to load big map
25.01.2022 Progress of new upper extension underway to existing home in Mudjimba
25.01.2022 A glimpse of the upper level frames
24.01.2022 Plastering and waterproofing all done ready for tiling and painting .
23.01.2022 Scaffold up ready to complete lockup
23.01.2022 External final look starting to take shape . Bluebeard section under gable window will be tiled .
23.01.2022 Cavity sliding door units installed for ensuite and walk in robe , and bulkhead to lower level covering ensuite plumbing
21.01.2022 Roof tiles all on , always good to have an upper level extension waterproofed
21.01.2022 Check out these windows, this is the same window double glazed with two opening options .
19.01.2022 Had all the steel beams installed today, went together perfectly .
19.01.2022 7.30 in the morning, we have just finished pouring the two little slabs required ready for the lower level extensions.
18.01.2022 Installed a few second hand cedar windows supplied by client into extension at Mudjimba .
17.01.2022 Big day today completing all the walls , now to brace and tie down the frame .
16.01.2022 Finished the floor sheeting , now started the framing . You can now start seeing the actual size of the extension.
15.01.2022 Start of a new job in wurtulla . New upper extension with modifications downstairs to lock up only . First stage is a couple of slabs to extend downstairs.
15.01.2022 Tiling to the bathroom and ensuite all completed with plumber installing all fixtures to complete the bathrooms.
14.01.2022 Internal finishing of the granny flat
13.01.2022 Hard to see through the scaffolding , external cladding starting to take shape
12.01.2022 New floor tiles installed to renovation in Pacific Paradise
12.01.2022 Had a busy week finally getting the floor sheeting on
11.01.2022 Existing roof structure removed ready for new second level floor system . Check out the ceiling insulation used , terrible stuff can you guess what it is ?
11.01.2022 Beautiful staircase to upper extension in Pacific Paradise
10.01.2022 Finally after the rain some positive progress with the construction .
09.01.2022 New ensuite and upgraded bathroom to home in Pacific Paradise
09.01.2022 Job in Burpengary taking shape after having scaffold removed.
09.01.2022 Progressing nicely with the upper extension.
09.01.2022 Finally got the roof on (good protection from the weather ) and eaves all completed to job in Mudjimba
08.01.2022 Doors from ensuite onto front decking
08.01.2022 Boys have done a good job this week at Wurtulla, frame finished, trusses on , ceiling battens and cyclone rods done now for the scaffold.
08.01.2022 Upper extension complete with deckings
07.01.2022 Start of a new job today in Burpengary before the demolition.
06.01.2022 Frame up on the extension in Mudjimba ready for fascia , guttering and roofing to be installed
04.01.2022 Busy day today , walls finished and trusses up
04.01.2022 Job progressing well floor joists finally all competed ready for floor sheeting
04.01.2022 Job at Pacific Paradise just about completed outside with the finishing touch to be done to complete everything
04.01.2022 Extension at Noosa progressing nicely , scaffold all completed waiting for colourbond roofing to be installed
03.01.2022 Started this little extension and renovation to a unit until the rain put a halt to it , hopefully next week will be better .
02.01.2022 Yesterday we installed eaves and windows , house is starting to take shape