Australia Free Web Directory

Integral Construction | Local service



Click/Tap
to load big map

Integral Construction

Phone: +61 7 5471 6322



Reviews

Add review



Tags

Click/Tap
to load big map

25.01.2022 PROJECT UPDATE - Thanks to Aurem Roofing for this fantastic footage of Coolum State High School's New Learning Centre. Spec's below of the Roof Sheeting installed on this building...



25.01.2022 Integral Construction will be closed for the Easter long weekend, back on site Tuesday 23rd April...wishing you all a Happy Easter!

24.01.2022 PROJECT UPDATE - The Adderton Refurbishment works has recently been completed by Project Manager - Mike Dawson, Site Manager - Bob Tedford, CA - Anelle Brink and a great team of Subcontractors and Suppliers. This was a heritage refurb of the former Convent. The refurbishment works will offer a range of exhibition spaces and activities for visitors. Professional photos to come..

23.01.2022 PROJECT UPDATE - at Coolum High School we are nearing completion; - 90% of Floor Coverings are down - 90% of Joinery is in - Touch up Painting is progressing - Scaffold is being progressively dropped... - Bitumen, Line Marking and Landscaping to complete in the new carpark and we are done! Well down to our site team, it is looking fantastic! See more



23.01.2022 PROJECT UPDATE - also at Matthew Flinders Anglican College Block J Refurbishment (Year 7) the Brickwork is near complete, Soffit linings going up and Windows to be installed along with the Balustrade this week, from there the Scaffold can be dropped. Well done to our Matthew Flinders project team! Stay tuned for further updates within the College...

22.01.2022 COVID-19 UPDATE: As you can see from our latest posts Integral Construction continues to operate as usual. The majority of our staff from our Head Office in Coolum and Brisbane have now moved to working from home and with the assistance of Microsoft Teams we are still able to meet regularly. The situation surrounding this pandemic is evolving daily and we are continuing to monitor health authority and government directives in this relation. The health and safety of all Inte...gral Construction employees, clients, subcontractors and suppliers continues to be of the utmost importance. We all need to take on the responsibility of protecting ourselves personally and our Workplaces to ensure we continue to operate to as close to normal during these uncertain times.

22.01.2022 PROJECT UPDATE - at Matthew Flinders Anglican College Block F (Year 5 & 6) the Blockwork is up and continuing and the Formwork and Scaffold contractors commence on site today. Our Matthew Flinders project team continue to do a great job throughout the school grounds on the multiple projects they are currently working on. Stay tuned for further updates within the College...



21.01.2022 COMMUNITY - Its not all work, work, work at Integral. This year we sponsored the Saints Rugby Club, a fantastic community of local families with children playing the game they love. Bring on the 2020 season..GO SAINTS!

21.01.2022 PROJECT UPDATE - Noosa Christian College's new Senior/Staff Building has been progressing quickly since our last update... Scaffold is now starting to come down, the Hospitality Air-Con is going in, Ceiling framing is going up, we are completing the External Cladding and the Joinery has commenced. Site Manager - Brad Ward

20.01.2022 WHAT IS YOUR GUESS? Noosa Christian College are having a competition to see who can guess the correct number of concrete trucks we used to pour our second slab...answer posted tomorrow!

19.01.2022 This afternoon we had the pleasure of attending the Official Opening of the recently completed St Andrews Aquatic Centre and the inaugural Diamond Splash for the students...

18.01.2022 PROJECT UPDATE - Finally some sunshine..and St Andrews Aquatic Center is looking good! Services are being fit-off, Equitone cladding is going up, Painting continues and Joinery is soon to commence. Brad and the team of trades on site are doing a great job!



18.01.2022 PROJECT UPDATE - Noosa Christian College 27/4/2020

18.01.2022 PROJECT FLASHBACK - 50 Wises Rd Commercial...this building always catches the eye driving down Wises Road right??!

16.01.2022 PROJECT UPDATE - Noosa Christian College (PART 2) has seen the Ground Slab prepd and poured over the past couple of weeks. Blockwork walls to stairs and load bearing walls has commenced and external wall and soffit framing has also begun.

14.01.2022 PROJECT UPDATE - Noosa Christian College (PART 1) has seen the Ground Slab prepd and poured over the past couple of weeks. Blockwork walls to stairs and load bearing walls has commenced and external wall and soffit framing has also begun. Thanks to our Site Manager - Brad Ward for the footage from his drone!

14.01.2022 TODAY MARKS INTEGRAL CONSTRUCTIONS 20TH BIRTHDAY! Our first project was an Office Building on Duke St in Gympie, followed by Caloundra City Autos. Since then we have completed roughly 242 projects (if you break it down it would work out to be 1 project per month for each of the 20 years). We wish to thank all of our Clients, Consultants, Subcontractors, Suppliers and in particular our Staff who have stuck with us along the way, some of which who have been with us for the enitre 20 years, and quite a few more who are upwards of 16+ years of service. This is a momentous occasion which we look forward to celebrating as a group at a later date...for now though, lets eat cake!

13.01.2022 PROJECT UPDATE - St Andrews Aquatic Centers signage has gone up this week, and you cant miss it! The project is coming together now with the finishing trades well underway. Not too much longer and well be filling the pool..

13.01.2022 PROJECT UPDATE - Matthew Flinders Year 7 Refurb...this footage courtesy of MFAC sums it up...our team on site have been BUSY over the past couple of months. Works are well and truely on track in both the Year 7 Precinct and the Years 5&6 Building. Well done to all subcontractors and suppliers involved... Project Team - Site Manager - Allan Connor Project Manager - Peter Shilkin... C.A - Anelle Brink See more

12.01.2022 PROJECT UPDATE - as you can see at Coolum State High School our team has been very busy... - Commencing Scaffold drop today - Ground floor vinyl commencing on site tomorrow - Level 1 corridor is ready for paint - Install of grid ceilings commencing to Level 1 classrooms... - Concrete being prepared this week for undercroft area Well done to our project team on and off site...this project is looking great! See more

11.01.2022 PROJECT UPDATE - Thanks to Aurem Roofing for this fantastic footage of Coolum State High Schools New Learning Centre. Specs below of the Roof Sheeting installed on this building...

11.01.2022 PROJECT UPDATE - Maryborough State High Schools Block J Refurbishment is just about complete, a few minor works to close out while the School moves in to their new Art Robotics, Coding and Online Conferencing Spaces. Well done to our project team for another successful build within the school. More photos to come...... Site Manager - Domenic Goebel Project Manager - Mike Dawson Contract Administrator - Lindsay Kruck

11.01.2022 NEW PROJECT - In the past month we have started a project at Matthew Flinders Anglican College - Temporary Facilities. We are in the midst of constructing 6 GLA Rooms with Office and Store Room Areas with Walkways linking into the existing College facilities. Site Manager - Allan Connor

09.01.2022 NEW PROJECT - Integral have been awarded and commenced works on site at Maryborough State High School's new Student Precinct & Futsal Courts, following are some drone shots shared with us by our SR. Works are due to for completion Feb 2021. Site Manager - Domenic Goebel

09.01.2022 Its time time to hang up the helmets!! From the Integral family to yours, we wish you all a VERY MERRY CHRISTMAS. We will be back on site (and in office) from Monday 6th January 2020. Cheers!

08.01.2022 PROJECT UPDATE - at St Peters Lutheran College, Indooroopilly - our team have been VERY busy working through the multiple stages of the Enabling Project works. Most recently the Science Lab Refurbishment. Below are some professional photos courtesy of our contractor Westlab...

07.01.2022 NEW PROJECT - It has been a busy few months for Integral as we have also picked up the Bundaberg State High School New Learning Centre project. Works have also commenced on site with project completion set for May 2021. Site Manager - Ethan Ferguson Further project updates to come...

07.01.2022 PROJECT UPDATE - Coolum State High School New Learning Center has been gaining traction over the past month. 90% of our Concrete pours are complete and Structural steel works are commencing on site. Well done to Site Manager - Ethan Ferguson and his team of trades on site...now to try and keep cool in this heat!

07.01.2022 PROJECT UPDATE - at Adderton Building, courtesy of Wilson Architects...

05.01.2022 AWARD WINNER!!! Congrats BHC, we are glad to be a part of such a successful community spirited project...well done!

04.01.2022 NEW PROJECT - Dacmar Rd Industrial...a little multi-unit tilt panel job to keep us busy If the weather stays like this well be done before you know it!! Site Manager - Ethan Ferguson

03.01.2022 NEW PROJECT - Matthew Flinders Anglican College - Year 5 & 6 Block F. Works commencing on site 9th December. Site Manager - Allan Connor Project Manager - Peter Shilkin C.A - Anelle Brink Keep an eye on the page in the new year for project updates!

02.01.2022 NEW PROJECT - Integral has been awarded the design and construction of the QFES Rainbow Beach Fire & Rescue Station. Design phase is currently underway with works to commence on site in early September. Well done team!

02.01.2022 PROJECT UPDATE - Coolum State High Schools New Learning Centre is near completion, we are in the final stages now with just finishing touches and some turf to go before we handover to the School in the upcoming weeks. Site Manager - Ethan Ferguson

02.01.2022 NEW PROJECT - back to Maryborough we go! We have been awarded the Maryborough SHS Block J Refurbishment project. Early works are due to kick off on site this side of Christmas. Further updates to come...

02.01.2022 PROJECT UPDATE - Noosa Christian Colleges new Senior/Staff Building has been progressing quickly since our last update... Scaffold is now starting to come down, the Hospitality Air-Con is going in, Ceiling framing is going up, we are completing the External Cladding and the Joinery has commenced. Site Manager - Brad Ward

01.01.2022 PROJECT UPDATE - and the Main Pool is FULL at St Andrews Aquatic Centre, approximately 2575kl of water has gone in over a 5 day period. Learn to Swim Pool is next to be filled. Only a few weeks left of Pool Commissioning, Landscaping and Cafe fitout works...

01.01.2022 PROJECT UPDATE - Aveo Morayfield is nearing the finish line. What a difference some greenery makes! Carpark and driveway pours are underway and final bits of fencing are being installed. Well done to Ethan, Dom, Doug and all the team of trades involved on site.

01.01.2022 Its not ALL work, work, work at Integral. On Sunday we had the pleasure of participating and sponsoring the Mooloolaba State Schools annual P&C Golf Day at Caloundra Golf Club. Our team placed in the top 10!

01.01.2022 NEW PROJECT - Noosa Christian College Senior & Staff Building. Another great project for the new year. We will be kicking off on site from 20th January 2020!

01.01.2022 Lest we forget 25/4/2019

Related searches